"GALLA PLACIDIA" PROJECT
CUSTOMER
Ancona Council

HEIGHT (FROM GROUND)
96 metres

CRANE CARRYING CAPACITY
80 tons.

OBJECTIVE
The Ancona Council has commissioned the restructuring of the Palazzo degli Anziani (Palace of the Elderly). The job consisted of transferring on the roof all the necessary building materials.
ANALYSIS The peculiarity of this project was given by the difficulties in reaching the actual Palace, situated inside the Old Town of Ancona, with a crane of a consistent mass that could have caused the cracking of the roads.
In collaboration with the engineers of the council, the current state of the streets was analysed and, most importantly, the presence of sub-services that with the transit of the crane could have been damaged and therefore caused inconveniences to citizens of the city.

STRATEGY Due to the fact that it was impossible to guarantee that the road network of the city would not cause any problem, it was decided to conduct the lifting from the street below the Palace. As a consequence, it was necessary to use a crane with a longer jib so that the materials could be place not only throughout all the height of the Palace but also so that they could have been place in the centre of the roof.
In this way we have mitigated all risks guaranteeing the success of the project with maximum security.

INSTRUMENTS The height of the building resulted in the use of the 80 ton crane with a 96 metre jib in order to lift in the most efficient way the materials that had a weight of a few quintals.
"GALLA PLACIDIA" PROJECT
CUSTOMER
Ancona Council

HEIGHT (FROM GROUND)
96 metres

OBJECTIVE
The Ancona Council has commissioned the restructuring of the Palazzo degli Anziani (Palace of the Elderly). The job consisted of transferring on the roof all the necessary building materials.
ANALYSIS The peculiarity of this project was given by the difficulties in reaching the actual Palace, situated inside the Old Town of Ancona, with a crane of a consistent mass that could have caused the cracking of the roads.
In collaboration with the engineers of the council, the current state of the streets was analysed and, most importantly, the presence of sub-services that with the transit of the crane could have been damaged and therefore caused inconveniences to citizens of the city.

STRATEGY Due to the fact that it was impossible to guarantee that the road network of the city would not cause any problem, it was decided to conduct the lifting from the street below the Palace. As a consequence, it was necessary to use a crane with a longer jib so that the materials could be place not only throughout all the height of the Palace but also so that they could have been place in the centre of the roof.
In this way we have mitigated all risks guaranteeing the success of the project with maximum security.

INSTRUMENTS The height of the building resulted in the use of the 80 ton crane with a 96 metre jib in order to lift in the most efficient way the materials that had a weight of a few quintals.
"GALLA PLACIDIA" PROJECT
CUSTOMER
Ancona Council

HEIGHT (FROM GROUND)
96 metres

OBJECTIVE
The Ancona Council has commissioned the restructuring of the Palazzo degli Anziani (Palace of the Elderly). The job consisted of transferring on the roof all the necessary building materials.
ANALYSIS The peculiarity of this project was given by the difficulties in reaching the actual Palace, situated inside the Old Town of Ancona, with a crane of a consistent mass that could have caused the cracking of the roads.
In collaboration with the engineers of the council, the current state of the streets was analysed and, most importantly, the presence of sub-services that with the transit of the crane could have been damaged and therefore caused inconveniences to citizens of the city.

STRATEGY Due to the fact that it was impossible to guarantee that the road network of the city would not cause any problem, it was decided to conduct the lifting from the street below the Palace. As a consequence, it was necessary to use a crane with a longer jib so that the materials could be place not only throughout all the height of the Palace but also so that they could have been place in the centre of the roof.
In this way we have mitigated all risks guaranteeing the success of the project with maximum security.

INSTRUMENTS The height of the building resulted in the use of the 80 ton crane with a 96 metre jib in order to lift in the most efficient way the materials that had a weight of a few quintals.

OUR BLOG

OUR BLOG

Be part of the discussion on our and on your projects! Get information, inform, communicate, share..
Lorenzo Binci / 01.09.2018
IL GRUPPO PEPA OTTIENE LA CERTIFICAZIONE ISO 45001:2018

Le aziende del Gruppo Pepa sono tra le prime in italia ad aver ottenuto la certificazione ISO 45001:...

read more
Lorenzo Binci / 21.12.2017
IL PARCO MEZZI PEPA SI AMPLIA: IN ARRIVO IL TRATTORE 8X4 E LA CULLA 2 ASSI

Le premesse, in termini di innovazioni ed investimenti futuribili, erano già ottime sin dallo...

read more
Lorenzo Binci
01.09.2018